Romania battery storage

Romanian developer Monsson has installed a 24 MWh battery storage system as the first stage of a 216 MWh project. The storage unit forms part of Romania's first hybrid PV-wind-battery system.
Contact online >>

Romanian developer Monsson has installed a 24 MWh battery storage system as the first stage of a 216 MWh project. The storage unit forms part of Romania''s first hybrid PV-wind-battery system.

Romanian developer Monsson has commissioned a 24 MWh (6 MW x four hours) battery storage system as part of Romania''s first hybrid photovoltaic-wind-battery project. 

Billed as the largest installed battery storage system in Romania to date, the storage unit represents the first stage of a 216 MWh project to be installed before the end of the year at the same location.

The storage unit is charged with energy produced by an operational 50 MW wind farm and a 35 MW PV project under construction, named Gălbiori 2, which is set to be grid connected by the end of 2024. It will be charged with energy from the national grid when there is no wind or sun.

Monsson said the storage unit concept is modular and suitable for large scale applications. It features lithium ion batteries produced locally by Romania''s Prime Batteries Technology and controlling software created by Monsson, so the hybrid project is fully automatic, without local operational staff.

Sebastian Enache, a Monsson board member, said the hybrid project is reducing the volatility of renewable energy and will lead to lower electricity bills for end consumers.

"With this project we are testing the functionality of the battery to demonstrate the immediate benefits of storage facilities attached to renewable energy sources. We want to promote such solutions both in Romania and across Europe," he said.

Energy specialist Corina Popescu said that the project is 95% Romanian and proves the country''s capacity to be part of the European Union''s transition to zero emissions.

The Romanian government plans to generate 36% of Romania''s energy from renewables by 2030. The country''s first renewables auction under a contract-for-difference scheme is forthcoming.

Your personal data will only be disclosed or otherwise transmitted to third parties for the purposes of spam filtering or if this is necessary for technical maintenance of the website. Any other transfer to third parties will not take place unless this is justified on the basis of applicable data protection regulations or if pv magazine is legally obliged to do so.

You may revoke this consent at any time with effect for the future, in which case your personal data will be deleted immediately. Otherwise, your data will be deleted if pv magazine has processed your request or the purpose of data storage is fulfilled.

Prime Batteries and Monsson put into operation the largest capacity of electric energy storage in batteries in Romania. This is part of the first hybrid photovoltaic-wind-battery project, within the Mireasa Wind Park, with a capacity of 50 MW, located in Constanța County.

The storage unit has an installed capacity of 24 MWh – (6MWx4h), it is built in Constanța county by Monsson, through a unique project pending patenting, and uses batteries of domestic production, produced by the Romanian company Prime Batteries Technology. This first stage is only one of the 3 stages that will constitute a total of 216 MWh of storage capacity that will be put into operation during 2024-2025.

The storage unit will be charged with energy produced by the existing 50MW Mireasa Wind Farm in operation, with photovoltaic energy produced by the 35MW Galbiori 2 Photovoltaic Park under construction and connected to the grid in 2024, as well as from the national grid when there is no wind or sun. The control of the hybrid project is fully automatic remotely, without local operational personnel and will work in an integrated system, through proprietary software developed by Monsson.

The investment is made from own sources and was initiated with the aim of reducing the volatility of renewable energy from its own portfolio, as well as to help balance SEN. Thus, it will ultimately help increase the penetration of renewable energies in Romania and reduce energy costs for end consumers by testing battery functionality to demonstrate the immediate benefits of storage facilities attached to renewable energy production sources.

The European Commission has approved, under EU State aid rules, a €103 millionRomanian scheme to support the construction of electricity storage facilities. The measure will be partly funded by the Recovery and Resilience Facility (''RRF''), following the Commission''s positive assessment of the Romanian Recovery and Resilience Plan and its adoption by the Council.

About Romania battery storage

About Romania battery storage

As the photovoltaic (PV) industry continues to evolve, advancements in Romania battery storage have become critical to optimizing the utilization of renewable energy sources. From innovative battery technologies to intelligent energy management systems, these solutions are transforming the way we store and distribute solar-generated electricity.

When you're looking for the latest and most efficient Romania battery storage for your PV project, our website offers a comprehensive selection of cutting-edge products designed to meet your specific requirements. Whether you're a renewable energy developer, utility company, or commercial enterprise looking to reduce your carbon footprint, we have the solutions to help you harness the full potential of solar energy.

By interacting with our online customer service, you'll gain a deep understanding of the various Romania battery storage featured in our extensive catalog, such as high-efficiency storage batteries and intelligent energy management systems, and how they work together to provide a stable and reliable power supply for your PV projects.

Related Contents

Contact Integrated Localized Bess Provider

Enter your inquiry details, We will reply you in 24 hours.